Revolt news212 of 15.7.06 and other issues are sent bcc and free. To
subscribe or unsubscribe simply email me. Email addresses which fail for
three consecutive issues will be removed in any case. For further
information please see .
For your convenience ... these news issues are usually in plain text
because attachments may take time to receive and may be difficult for
some to open. We try to keep it simple.
1. Snips from news@all-energy issue 67 of early July 06 are at
APPENDIX A.
2. An article from New Scientist 8 July 2007 (APPENDIX B) discusses
ecological impact of wind turbines, particularly on peat, with reference
to the Derrybrien "bogalanche" land slide.
3. More from Ireland - Toby Hall writes of representations to the EU
about pylons in Sligo and Roscommon (APPENDIX C).
4. A Scottish Parliamentary motion on the Beauly-Denny powerline is
being drawn up by Roseanna Cunningham MSP (APPENDIX D). Comments are
invited.
5. The DTI Energy Review was published 11-7-06 and is available at
.
The full report is over 3MB but it can be downloaded by chapters. At the
same time, Alistair Darling launched the Government's Energy Green Paper
in the House of Commons, to be followed by further consultations on some
details, including key renewable aspects, before an Energy White Paper
early in the new year. The effect is to retain nuclear generation while
still promoting renewables, and to reduce local planning control of
both.
6. DEFRA is repositioning under new SoS David Milliband, who is said to
have other ambitions. Their magazine Energy (etc.) Management has little
other "new" news. A news-in-brief item "Grid Upgrade" reminds us NG is
to invest more than 12 billion pounds over 5 years mainly on gas and
electricity infrastructure. "Deputy Chief Executive Steve Holliday said
transmission charges were such a small proportion of overall energy
costs that the cost impact on consumers would be very small." [So
presumably 12 billion spent on burying powerlines wouldn't have much
impact either?] NG reported pre-tax profits up by 11% to £1.9 bn.
*****
*****
APPENDIX A Snips from news@all-energy issue 67 of early July 06.
3.1.Ofgem urges investment
Energy regulator Ofgem says gas and electricity network operators should
invest £4bn over the next five years to meet rising demand
- less than the companies' initial submission of £6.7bn.
3.2.£700m for Scotland
Energy regulator Ofgem earmarked £700m for investment by Scotland's two
utility giants in the nation's electricity networks over the next five
years
3.6.Power line veto 'could harm' green energy sector
Campaigners against the upgrade of a main electricity power line down
the spine of Scotland risk destroying the burgeoning renewable energy
sector
5.WIND NEWS - INTERNATIONAL
>The USA's first commercial plant using wind power to produce hydrogen
was to be unveiled in Idaho
6.1.Wicks welcomes green light for Climate Change Bill
Royal Assent was given for a Private Member's Bill that will make it
easier for householders who produce electricity from microgeneration
technologies at their homes to sell unused power back to their supplier
6.2.Planning restrictions to be lifted
The government is to sweep away planning restrictions so that millions
of homeowners can put wind turbines and solar panels on their houses
*****
*****
APPENDIX B The hidden cost of wind turbines, New Scientist Print
Edition
Ed Douglas 08 July 2006
It started with Turbine 68. On 16 October 2003, following excavations
for the 49-metre tower's massive foundations, the peat bog above the
village of Derrybrien in county Galway, Ireland, began to move. That
night almost half a square kilometre of bog slid 2.5 kilometres down the
hillside, engulfing an unoccupied farmhouse and blocking two roads.
Journalists dubbed it the "bogalanche", and speculated about what might
have happened had the weather been wet. Two weeks later they found
out. Heavy rains washed peat soup into the Abhainn Da Loilioch river,
where the sludge killed 50,000 fish and affected 50,000 more.
Anxious not to delay Ireland's renewable energy programme, politicians
reassured local people that the bogalanche was an isolated incident. The
operators were fined ¬1250 for polluting the river, they adopted new
working practices, and completed construction of the 71-turbine project
to create Ireland's largest wind farm. But the residents of Derrybrien
were not prepared to leave it there. They felt ignored by the
planning system and uncertain about what might happen next, so they
commissioned their own report. The findings highlighted various
shortcomings of the project, and concluded that the environmental impact
assessment had failed to consider the implications of constructing major
infrastructure on a peat bog. As a result, the European Union is now
prosecuting the Irish government in the European Court of Justice.
What happened at Derrybrien was not a major environmental catastrophe,
certainly not compared to the ravages of global warming, but it is a
cautionary tale. If Ireland, and the rest of the world, is going to use
wind energy to reduce greenhouse-gas emissions, there are going to have
to be an awful lot more installations like Derrybrien. The problem is
that in our haste to cash in on the obvious environmental benefits of
wind power, we are largely ignoring the ecological damage that turbines
can do. It is not simply a matter of sliding peat bogs. Some ecologists
are warning that unless we think carefully about where wind farms are
sited, they could disrupt fragile ecosystems and even contribute to
global warming.
The stakes for wind energy are sky high. Seen by many as the major
renewable alternative to fossil fuels, it is the world's fastest-growing
source of power. In 2005, the world's installed wind power generation
capacity increased by 43 per cent to almost 60,000 megawatts - that's
more than 12 times Ireland's total electricity demand. Almost 70 per
cent of this is in Europe, and while less than 20 per cent is in
North America that figure is rising rapidly (see Diagram). Last year
alone, US companies spent $3 billion on 2300 megawatts of new wind
energy capacity, bringing its total to 9149 megawatts - a little more
than 1 per cent of total US generating capacity. Other countries are
also catching up fast. India is already fourth in the wind-energy league
table, having overtaken Denmark, and China has plans to build 5000
megawatts of wind power capacity by 2010.
Worldwide, wind energy still accounts for little more than 0.5 per cent
of total electricity generation, but expectations are high. The US
government believes wind could supply up to 20 per cent of the country's
electricity. Other estimates are even more impressive. Last year,
Christina Archer and Mark Jacobson from Stanford University in
California produced a global wind-energy resource map that estimated
the global potential for wind-generated energy at 72 terawatts - that's
40 times the worldwide demand in 2000 (Journal of Geophysical Research -
Atmospheres, DOI: 10.1029/2004JD005462). It is not surprising that
governments have looked at growing electricity demand and the public's
fears about global warming, and seen wind energy as part of the
solution.
But there is a problem. Where do you put hundreds, if not thousands, of
wind turbines? The obvious answer is a windy place in the middle of
nowhere. In crowded Europe, at least, that often means taking the same
option as the Derrybrien developers and building wind farms on peat
bogs. In the UK, such farms include the 59-megawatt Cefn Croes in mid-
Wales, which was the country's biggest wind farm when it opened last
year, and a proposed 234-turbine, 702-megawatt installation on
the Lewis Peatlands Special Protection Area in Scotland's Outer
Hebrides. "Rolling hills near the sea offer the right kind of wind, and
those are also the right conditions for bogs," says peat expert Richard
Lindsay from the University of East London, who compiled the report for
the Derrybrien residents along with colleague Olivia Bragg.
Lindsay is an advocate for renewable energy but has become concerned by
the scale and number of wind-farm developments on peat bogs in Europe.
"This is the Cinderella ecosystem," he says. "Peatland is busy
performing a series of important functions for us and we just don't see
it." Bogs often play a critical role in providing clean drinking water.
More significantly in the context of renewable energy, they store
three times as much carbon as is held in tropical rainforests. "We build
wind farms in order to reduce carbon emissions," Lindsay says. "Yet
peatlands represent the one land-based habitat in the world that is a
major long-term carbon store. By building on peat, we release this
carbon store as carbon emissions into the atmosphere." 'Peat bogs store
three times as much carbon as is held in tropical rainforests'
This can happen in several ways. Peat dug out for foundations and
service roads is stacked up and allowed to dry, and as it does so the
carbon it contains - 55 kilograms per cubic metre - oxidises and is
released into the atmosphere as CO2. Construction on peat can also lead
to widespread damage of a bog's integrity. Disruption of part of a bog
can affect the whole ecosystem - in that respect, peatland acts more
like a body of water than land, Lindsay explains. The results in this
fluid environment are unpredictable, but can range from erosion of
varying intensity to a catastrophic event like the one at Derrybrien.
Lindsay and Bragg calculated that the Derrybrien bogalanche released
enough CO2 to nullify the carbon savings during the lifetime of two of
the turbines there. Even when the ecological impact of turbines is less
dramatic, carbon emissions can still be substantial. Mike Hall from the
Cumbria Wildlife Trust in north-west England has developed a formula to
give a wind-energy CO2 "budget" that balances the CO2 savings that a
project is expected to provide against the CO2 costs from the
manufacture and shipping of the turbines and construction work at the
site.
The CO2 costs are considerable even before accounting for emissions from
peatland, primarily because of the energy required to produce the
concrete in which turbines are embedded. The new generation of 140-metre
turbines, need foundations the size of half a football pitch. Building
on peat bogs contributes another large source of CO2 that can add years
to a turbine's CO2 payback time. "The major CO2 debt incurred by a wind
turbine on a peat-rich site is not in its manufacture and installation
but in the ongoing degradation of peat," Hall says.
Payback time
Hall has devised three scenarios for CO2 emissions from degrading peat.
The first is a baseline figure calculated simply from the amount of peat
excavated in construction. The second "minimal scenario" includes
emissions from degraded peat up to 50 metres around areas of disturbance
such as foundations and service roads. This figure is being used by wind
farm developer AMEC in Scotland. A third "high scenario" extends that
range to 100 metres. Hall believes this is closest to the actual level
of disruption, citing Lindsay's research, which indicates that damage to
peat can extend for as much as 250 metres on either side of tracks or
drainage ditches, as water drains from the affected area.
To calculate carbon savings, Hall uses the developers' own predictions,
which generally give figures for overall electricity generation of about
30 per cent of the maximum rated capacity of a turbine. The average
achieved output for existing wind farms is actually lower than this -
25.6 per cent according to industry figures. Using the conservative
"minimal scenario", Hall calculates that a 2-megawatt turbine built
on peat moorland 1 metre deep will take 8.2 years to pay back its CO2
cost. The figure for the "high scenario" is a whopping 16 years. Even
the minimal figure is a substantial portion of a turbine's normal
lifespan of 25 years, and considerably higher than the industry's own
figures, which range between three and 18 months.
Developers sometimes promise to avoid some of these emissions by, for
example, using "floating roads". "I call them 'sinking roads'," Lindsay
says, having witnessed the fate of floating roads at Derrybrien. Worse,
he believes environmental impact assessments completed by developers on
peat bogs are often either flawed or incomplete. "Should we be
developing energy systems on the landscape that is our main carbon store
and which releases carbon when you build on it?" he asks. Put that way,
the proliferation of wind farms on peatland does seem somewhat
foolhardy. But what are the alternatives?
In the US and Australia many wind farms are built in desert regions. The
ecological impact in these environments is largely unstudied. Somnath
Baidya Roy from Princeton University and his team have done research
suggesting that rotating turbine blades lead to desiccation of the
surrounding area, which may be particularly damaging in deserts (Journal
of Geophysical Research Atmospheres, DOI: 10.1029/2004JD004763). In
addition, a recent study of Californian ground squirrels reveals that
those living close to wind farms are more edgy and cautious than those
that inhabit areas of desert where there are no turbines. Lawrence Rabin
from the University of California, Davis, and colleagues conclude that
this is likely to have a knock-on effect within the ecosystem, affecting
species including golden eagles, red-legged frogs and California tiger
salamanders. They, like Lindsay, argue for greater care in siting
turbines to minimise their ecological impact.
In Europe, the main alternative to peat bog sites is to go offshore.
Denmark leads the way. By 2030, it will have an offshore capacity of
4000 megawatts - around 40 per cent of its total electricity
requirement. The UK also has big ideas, with 13 projects of
up to 30 turbines each already approved, and a goal of achieving half
its renewable target for 2010 with offshore turbines. Research into the
ecological impact of offshore renewable energy developments is even
sparser than for onshore projects.
Writing in the Journal of Applied Ecology last year (vol 42, p 605),
Andrew Gill from the Institute of Water and Environment at Cranfield
University in Silsoe, Bedfordshire, UK, noted that only 1 per cent of
all papers on renewable energy published in the past 15 years considers
environmental impacts onshore, and none offshore. We have very little
idea how offshore installations will affect the marine environment and
disrupt its wildlife through habitat damage, noise and vibration,
electromagnetic fields and collisions with turbines, he warns. The
marine ecosystem is largely uncharted territory, so wind farm developers
often have no way of knowing which sites might be less vulnerable.
This lack of basic ecological information is also a major concern to
Mark Avery, conservation director for the UK's Royal Society for the
Protection of Birds. "You would think, with the industry being more
advanced in other countries, that there would be papers you could just
pull off the shelf," he says. Yet even figures on bird collisions with
turbines, a long-standing bone of contention, is limited (see "Watch
the birdie"). "Climate change is very bad news, and we're convinced we
need to reduce greenhouse gas emissions," says Avery. "Renewables,
including wind energy, have a part to play. The problem is where to put
them."
We will need a lot more research to answer that question. In the
meantime, though, there is an alternative to building huge wind farms in
vulnerable habitats. We could all install our own personal turbines on
the roofs of our houses. "I do believe that micro-generation has an
important part to play," Lindsay says.
Ed Douglas is a writer based in Sheffield, UK
From issue 2559 of New Scientist magazine, 08 July 2006, page 36
*****
*****
APPENDIX C from Toby Hall
Later this week the EU In Brussels will be hearing Roy Henry's petition
against the environmental impacts of the ESB's Flagford to Srananagh
220,000 kV line.
The full text of the petition can be seen at
[Attached is a photograph of one of the pylons already erected in
Roscommon.] As you can see these pylons will forever destroy the Sligo
and Roscommon landscape.
Why has there been no oral hearing about the truth and facts of this
project in Ireland, despite repeated efforts of the communities for six
years?
The EU hearing is on a limited aspect of the effects.
Although this project will for ever devastate a magnificent unspoilt
Ritual Sacred Landscape containing many hundreds of known archaeological
sites, especially some of the countries earliest astronomically aligned
chambered cairns, a 100-ft plus pylon will be sited 50 meters from the
Tinacarra dolmen!!
Failure by the County Councils, an Bord Pleanála, and Dúchas/The
National Monuments section of the Department of the Environment,
Heritage and Local Government, to fully appraise or evaluate the
development, have in large part been due to misinformation and lobbying.
No oral hearing was allowed, many questions remain unanswered, and due
process circumvented. People and businesses have left the region and
more are leaving, others are not coming, the region is about to be
needlessly blighted.
The EIS even confused the Carrowmore where the pylon pictured below is
situated with Carrowmore below Knocknarea 25 miles away!
The people deserve better.
Those who examined this project from a balanced perspective have found
it to unnecessary and unwise. It is a travesty that has already caused
great harm.
Sincerely,
Toby Hall.
www.all-energy-matters.org
*****
*****
APPENDIX D Scottish Parliamentary motion on Beauly-Denny powerline.
Roseanna Cunningham MSP is considering tabling a Parliamentary motion
asking for more consideration of the benefits of burying the power line
underground. She was planning to mention the Braco Pylons Campaign, and
I was wondering if you had any comments on the proposed text. The draft
motion is below for your information.
Many thanks in advance,
Sheena Cleland
Parliamentary Assistant to Roseanna Cunningham MSP
Tel. 0131 348 6087 Extn. 86087
"That the Parliament notes the suggestion by Perth and Kinross Council,
the Highland Council, the Cairngorm National Park Authority, the John
Muir Trust, and Scottish Natural Heritage that certain sections of the
proposed Beauly to Denny electricity transmission line be buried
underground; notes the work of the Perthshire-based Braco Pylons
Campaign, which promotes awareness of the positive aspects of
undergrounding power lines, including the benefit of decreasing
EMF exposure limits; and the work of other campaign groups throughout
Scotland who want further consideration of the undergrounding option;
notes that the Olympic Delivery Authority is spending up to £200 million
burying transmission lines in order to clear the site for London?s new
Olympic Park for the 2012 Games; and calls on the Scottish Executive not
to make any decision on the plans for the Beauly to Denny
power line until the option of burying cables underground has been fully
explored."
*****
*****
--
Mike O'Carroll